Go to Fortress Home Page Search the Fortress Website Print this Page
Case StudiesCase Studies. Explore the many uses and applications of carbon fiber technology
Videos & ArticlesVideos & Articles. Read and watch videos and articles on Fortress and carbon fiber uses.
NewsNews. Read about the latest news from Fortress Stabilization.
Frequently Asked QuestionsFrequently Asked Questions. Commonly asked questions.
Calendar of EventsCalendar of Events. What's happening now and in the future at Fortress.
TestimonialsTestimonials. Read what others have to say about Fortress and Carbon Fiber applications.
Locate InstallersLocate Certified Installers. Find a certified Fortress installer.
Link to UsLink to Us. Provide a link to Fortress Stabilization on your Website.
NewslettersThe Fortress Newsletter. Read current and past issues of our Newsletter.
Concrete RepairConcrete Repair Carbon-fiber technologies in concrete repair
Foundation RepairFoundation Repair Carbon-fiber technologies in foundation repair applications
Concrete ReinforcementConcrete Reinforcement Carbon-fiber technologies and reinforcement of concrete
Bowed basement wallsBowed Basement Wall Carbon-fiber technologies application in the reinforcement of bowed basement walls

Case Studies
Print this page
Date: January 2006
Structure: Segmental Bridge I-75 connector to Sawgrass SR869, Fort Lauderdale, Florida
Contractor: Lanford Brothers, Rounokee VA. MJ construction, Tarpin Springs FL.
Engineer: Florida D.O.T. Larry Sessions. PE.
Material Used: FORTRESS Carbon/Kevlar Grid 24K 8" wide with 4020 epoxy resin

Project Scope:
Waterproof segmental joints to control long term water infiltration into tension tendons.



Solution:
Previous method was to saw cut and fill with low modulas epoxy. New method: 4020 was utilized as waterproofing membrane; carbon/kevlar grid was used to strengthen and transfer the load across the joint. After joints were waterproofed, E-Bond 526-HV epoxy overlay was used to overlay the entire bridge surface. 15,580 linear ft of carbon/kevlar was placed and cured at amibient temperatures.



Observations:
Entire project was completed in under 55 days, including 2,000 ft. of carbon/kevlar joint per day. After being open to traffic for over a month, there are no signs visual cracking in the overlay that had occurred when using saw cut method only a short time after being opened to traffic.